Plans for expanded pickleball facilities at Lembi Community Park, a new Johnny Cash-themed art attraction and additional parks, trails and roadway improvements were among dozens of projects highlighted before members of the Folsom City Council at Tuesday night’s meeting, as city officials presented an extensive progress report on approximately $363.1 million in ongoing and planned capital improvements.

Advertisement

The Folsom City Council received its first quarterly capital projects report for the 2026-27 fiscal year, outlining where major city projects currently stand, what progress has been made and which milestones residents can expect in the months and years ahead. The informational presentation covered projects ranging from recreational facilities and pedestrian crossings to major roadway improvements, water infrastructure and sewer system upgrades.

Rather than introducing or approving the projects as part of the presentation, the report provided an overview of work already underway, previously authorized improvements and proposals still moving through planning, design or funding processes. Some projects are approaching completion, while others remain years away from construction.

Advertisement

The quarterly report, prepared by the city’s Capital Project Team, covered work managed by the Parks and Recreation, Public Works and Utilities departments. The update reflected project activity through mid-October and identified upcoming construction schedules, design milestones, funding efforts and community outreach opportunities.

Lembi Community Park pickleball expansion moves toward design

Advertisement

One of the recreational projects attracting community interest is the proposed expansion of pickleball facilities at Lembi Community Park, where city officials are continuing to develop plans following public outreach conducted in September.

According to Tuesday’s report, city staff completed an online community survey and hosted a public outreach meeting Sept. 17 to gather feedback on the proposed expansion. That input is now being incorporated into the project’s scope as officials prepare to move into the design phase.

Advertisement

The city is finalizing the project scope and issuing a request for proposals from professional design firms. An updated project overview is expected to be presented to the Folsom Parks and Recreation Commission and City Council by December, providing residents with additional information about the direction of the proposed improvements.

The expansion remains in its planning phase, meaning construction dates and final design details have not yet been established in the quarterly report. The upcoming presentations are expected to provide a clearer picture of how the city intends to move forward with expanding pickleball opportunities at the park.

Advertisement

The city’s 2026-27 capital improvement budget includes $400,000 for the Lembi Community Park Pickleball Expansion project. That funding does not represent approval of a final construction plan, and the report does not specify the number of additional courts proposed or a projected completion date.

The Folsom Parks & Recreation Department is exploring opportunities to expand pickleball facilities, renovate the existing basketball court, and enhance recreational amenities at Lembi Community Park.

Advertisement

During a September 17 community outreach meeting, residents reviewed three proposed improvement options and provided feedback. Of those who voted, all supported Plan C, which includes four additional pickleball courts, renovations to the existing basketball court, and other park enhancements.

The project remains in the planning stages, and no final plans have been approved. The Folsom Parks & Recreation Commission will review the proposed improvements on Tuesday, November 3, and consider whether to recommend that the City Council move the project forward.

Advertisement

Johnny Cash Trail art experience nearing installation

Another project approaching a significant milestone is the Hello, I’m Johnny Cash Art Experience along Folsom’s Johnny Cash Trail, where a new sculpture is expected to be installed before the end of the year.

Advertisement

The city reported that Romo Studios is currently fabricating the artwork, with installation anticipated before Dec. 31. RRM Design Group is simultaneously preparing the associated landscape design that will complement the installation.

The planned bronze sculpture will depict Johnny Cash seated on a stool with his guitar, creating another public art attraction celebrating the musician’s connection to Folsom. The installation is planned for city-owned property near the Johnny Cash Bridge, adding to the collection of artwork envisioned along the recreational trail.

The project follows the installation of Cash’s Pick No. 1, a 7-foot-tall guitar pick sculpture unveiled near Rainbow Bridge in November 2024. That installation marked the beginning of a larger public art experience designed to celebrate Cash’s historic 1968 performances at Folsom State Prison and his enduring connection to the community.

The Hello, I’m Johnny Cash sculpture was selected after federal officials declined to authorize the originally proposed second guitar pick installation on Bureau of Reclamation property. The city subsequently worked with state officials to redirect existing grant funding toward the alternative sculpture, allowing the public art program to continue.

A public celebration marking completion of the new art experience is tentatively planned for January 2027. The event would provide an opportunity for residents and visitors to see the completed installation and recognize another addition to the trail’s growing collection of Cash-inspired attractions.

New parks and recreational facilities continue through planning and construction

Beyond pickleball and the Johnny Cash Trail, the city’s quarterly report detailed progress on several park development projects intended to serve both established neighborhoods and growing areas of Folsom.

At Community Park East, preliminary conceptual planning is underway in preparation for future public outreach. City officials are also evaluating potential locations within the project area for a future library and municipal services center, a development that could eventually expand public services in that portion of the community.

The Ernie Sheldon Park Revitalization Plan is also progressing, with staff working toward a construction-ready design while developing strategies to fund the improvements. The city’s goal is to begin the bidding process in spring 2027, although the report does not establish a construction start date.

Benevento Family Park is further along in the design process. The city completed its initial design development and 30% construction documents in July, followed by 60% construction documents in September, with the next design milestone scheduled for October.

Environmental review is also advancing, with documentation under the California Environmental Quality Act scheduled for public circulation in November. Tribal consultation has begun, and a survey of the site is scheduled for Oct. 30.

Jack Rabbit Hill Park is another project moving through the design process after the City Council approved its master plan in May. The city received 90% construction drawings Oct. 8, with an expedited review scheduled to follow.

Construction is already underway at Livermore Community Park Phase 5A, where work began July 29 following the earlier award of a contract to Frontline General Engineering Construction. Grading and earthwork were expected to be completed in late October, with overall construction scheduled for completion by the end of January, weather permitting.

The city also reported substantial completion of the Mangini Ranch Trails project. Additional post-and-cable fencing was scheduled for completion in October, and a ribbon-cutting ceremony was scheduled for Wednesday, Oct. 28.

Meanwhile, Castle Park’s playground replacement and landscape renovation project has reached completion. The renovated playground reopened June 30, and the city completed its final project expenditure reconciliation in September.

Trail improvements and pedestrian crossings progress

Several projects aimed at expanding pedestrian and bicycle connections are also moving through planning and design, including proposed crossings and improvements along some of Folsom’s most heavily traveled corridors.

The East Bidwell Pedestrian Overcrossing project remains in the design process after city staff developed preliminary alignment alternatives and discussed them with stakeholders during the summer. A community outreach meeting was held Oct. 1 to review potential alignments and preliminary aesthetic concepts for the structure.

The Folsom Boulevard Bicycle and Pedestrian Overcrossing project is awaiting decisions on state and federal grant applications. The city submitted requests for funding through the federal Safe Streets and Roads for All program in May and California’s Active Transportation Program in June.

Further design work on that project will depend on the outcome of the funding applications. City officials have not established a construction schedule in the latest report.

Work is also progressing on the Highway 50 Class I Undercrossing and Trail Improvements project. Preliminary plans were completed in July, followed by coordination with the California Public Utilities Commission concerning railroad crossing requirements and setbacks.

The design team is incorporating recommendations from that review into updated plans. The next stage of design was scheduled for submission during October.

Along the Folsom-Placerville Rail Trail, engineers are finalizing construction documents for the segment between Iron Point Road and Broadstone Parkway. Construction of that portion is anticipated to be coordinated with improvements associated with adjacent development.

The White Rock Road Class I Trail project is approaching construction bidding after receiving authorization from Caltrans in July. The city anticipated advertising the construction bid package during October.

Additional trail renovations are being planned along the Humbug-Willow Creek Trail corridor. City staff completed a draft scope of work in September and expect to advertise the project for construction in November.

Prairie City Road improvements remain several years away

One of Folsom’s more significant transportation projects, the Prairie City Road Operational and Improvement Project, continues moving through planning and coordination with Sacramento County.

The city reported that intermediate pavement restoration and preservation work has been completed in cooperation with the county. Those improvements address existing roadway conditions while the larger operational improvement project continues through its development process.

According to the latest schedule, construction of the primary improvements is forecast to begin in late 2028 or early 2029. The timeline places the larger project several years away, although preliminary work and coordination remain underway.

Another major transportation investment is the proposed Empire Ranch Road interchange, which remains in the design and approval process. The project’s draft report has been circulating through Caltrans for final signatures, while city staff prepare an amendment covering final design, right-of-way acquisition and utility coordination.

That amendment is expected to reach the City Council in January. Construction is currently forecast for spring 2029, contingent upon securing construction funding.

East Bidwell Road project receives $6.89 million grant

The city’s East Bidwell Operational and Pavement Rehabilitation Project received a significant financial boost with the award of a $6.89 million grant from the Sacramento Area Council of Governments.

The project is moving through design and engineering, with preliminary pavement design and geotechnical reports completed. Public outreach workshops are underway as the city continues evaluating roadway improvements.

The traffic analysis has also been updated to account for right-of-way dedication associated with the future Raising Cane’s location on Iron Point Road. That coordination is being incorporated into the broader planning process for improvements along the corridor.

Folsom Lake Crossing is also scheduled for additional safety improvements. The second phase of that project has been expanded to include additional paving, and environmental reevaluation is underway.

Construction is forecast to begin in spring 2027 and is expected to require approximately 30 business days. The schedule remains subject to completion of the remaining project requirements.

Street resurfacing and neighborhood improvements continue

Folsom’s ongoing pavement maintenance program is continuing into the 2026-27 fiscal year, with work planned in multiple residential neighborhoods.

Under the city’s Paving the Way program, neighborhood crack-sealing projects are underway in Empire Ranch, The Parkway, Willow Springs, Natoma Station and Prairie Oaks. Design plans for the current fiscal year’s improvements are also being developed.

The city anticipates beginning comprehensive slurry-seal construction in spring 2027. The work is part of Folsom’s continuing effort to maintain existing streets and extend pavement life.

The Central Business District Complete Street Project is another long-range improvement initiative. The city has submitted a grant application for approximately $1.1 million in planning, environmental and design funding toward a project currently estimated to cost $6.6 million.

Environmental work is forecast to begin in July 2027, followed by design in December 2027. Construction is tentatively scheduled for spring 2029.

Other transportation projects include planned improvements at Broadstone Parkway and Golf Links Drive, which are being incorporated into the city’s Intelligent Transportation System Master Plan implementation. Combining the work is intended to improve scheduling and cost efficiency.

The Riley Street Safety Improvement Project is also progressing through design, with the city seeking approximately $10 million in construction funding through a regional grant application.

Historic Folsom infrastructure upgrades planned

Major underground utility improvements are also being planned in Historic Folsom, where aging water and sewer infrastructure will be replaced through a substantial rehabilitation project.

The Basin 4 Phase 2 Sewer and Water System Rehabilitation Project includes replacement of approximately 8,000 linear feet of sewer mains and 2,800 linear feet of water mains in the Historic District north of Natoma Street.

The city has finalized right-of-way requirements and expects to complete design and advertise the project for bids during the second quarter of 2027. Construction is anticipated to begin in fall 2027.

The work follows the first phase of the Basin 4 sewer rehabilitation project, which involved approximately 3,200 linear feet of sewer mains in the Historic District. That earlier phase is substantially complete, with final restoration and closeout activities underway.

Other utility improvements include rehabilitation of water storage tanks, replacement of operating valves at Willow Hill Reservoir Dam and upgrades to water and wastewater communications systems.

The city is also updating its water and sewer master plans to evaluate long-term infrastructure needs and establish priorities for future investments. Those planning efforts will help guide projects and spending decisions in coming years.

More facility improvements approaching completion

Several smaller but important municipal facility projects are also nearing completion or preparing for construction.

At the Folsom Public Library, roof replacement work is underway and was expected to be completed by the end of October. Exterior painting at the City Hall campus began earlier this month and is scheduled for completion in December.

The Steve Miklos Aquatic Center is preparing for a pool heater replacement project, with work anticipated in January 2027. The project is among the facility maintenance improvements included in the city’s current capital program.

At the Andy Morin Sports Complex, staff are preparing a cooperative purchasing agreement with Musco Lighting for a prefabricated futsal court. The project remains in the planning phase, with additional details expected as the purchasing process advances.

The city is also assessing the condition of its water treatment plant and booster pump stations to identify future maintenance, rehabilitation and replacement needs. Those evaluations are intended to support long-term reliability of Folsom’s water system.

City overseeing more than $363 million in capital projects

Taken together, the projects represent approximately $363.1 million in capital improvements being managed during Folsom’s 2026-27 fiscal year. The program encompasses parks, recreational facilities, transportation infrastructure, trails, stormwater systems, water facilities and sewer improvements.

The figure represents the broader capital project portfolio rather than $363.1 million in new spending approved Tuesday night. The quarterly presentation was informational, with staff recommending that the City Council receive and file the report.

Individual projects remain subject to their respective approval processes, and some will require additional funding, contracts or formal council action before proceeding. City officials also cautioned that projected schedules remain subject to funding availability, regulatory approvals, construction bidding, weather and other project-specific conditions.

The Capital Project Team was established by the city manager to improve coordination among departments and provide regular progress reports to elected officials and the public. The next quarterly update is scheduled to be presented to the City Council in February 2027, when additional details are expected on projects advancing through design, bidding and construction.