The City of Folsom is home to more than six miles of frontage on the American River and Lake Natoma and now, the City of Folsom is seeking input from the community on what could be a very important part of the waterfront’s future.

 The city’s General Plan calls for the preparation of a River District Master Plan to activate Folsom’s expansive waterfront for improved access, recreation, and economic development. The area is located on the American River at Lake Natoma and is bound by Folsom-Auburn Road, Greenback Lane, and Folsom Boulevard.

Advertisement

The city and its consultant team have working on this topic for some time, and now, they are seeking input on the River District area. Community members are encouraged to weigh in and inform the master planning process on a new interactive engagement platform available on the city’s website.

 A community mapping activity and questionnaire are the first steps to gathering feedback on community preferences, needs, issues, and opportunities within the River District Master Plan area. We want to hear your thoughts—the online survey and mapping tool is available through Wednesday, January 17. 

Advertisement

Learn more, share your opinion, and sign up for updates on the website at: www.folsom.ca.us/RiverDistrict

Folsom River District background

River District Master Plan Key Objectives

Advertisement
  • Increase public access to the river and lake.
  • Increase recreation opportunities.
  • Increase economic development opportunities.
  • Commit to high-quality design.
  • Enhance Folsom’s heritage.
  • Celebrate and protect our environmental, cultural, and historical resources.
  • Recognize city gateway opportunities.
  • Integrate old and new areas of the city.

Advisory Committee

Advertisement
  • On January 24, 2023, the City Council directed the creation of an advisory committee. The committee will be comprised of stakeholder organizations and businesses within the district, residents, land managers, and resource representatives.
  • The committee is expected to form in late spring or early summer 2023 and will exist for up to one year.

The committee will provide a sounding board for a selected planning consultant to test ideas, challenge assumptions and ultimately make recommendations to the City Council. Recruitment is underway for a planning consultant experienced with the complexities of community planning, urban design, environmental and cultural resources, federal and state coordination, recreation, and community engagement.

Funding

Advertisement

On April 12, 2022, the City Council approved using American Recovery Plan Act (ARPA) funds to create a River District Master Plan. The master plan process will address substantial community interest in the following:

  • Improving access to Lake Natoma (American River) and elevating its place in the community related to tourism, recreation, business and commerce.
  • Protecting and celebrating historically and culturally significant sites.
  • Preserving significant habitat and environmental resource areas.

Property Within the River District

  • Federal and state properties comprise more than 75% of the land within the River District. The city must work closely with California State Parks and the Bureau of Reclamation while following the framework of their planning documents.
  • The remaining riverfront areas owned by the city and private property owners present unique and exciting opportunities.

Project Schedule

The schedule is tentative and subject to change.

  • February 2023: Distribution of consultant Request for Qualifications (RFQ).
  • March 2023: Consultant responses are due.
  • April 2023: Consultant shortlist established and scope of work proposals due.
  • May 2023: Consultant interviews, selection, and contract award.
  • June 2023: Project planning begins.
  • Fall 2024: Master Plan complete.